Photography and website timeline
Lisa Brookins Rental Website | kept up by Levi Ewald, Red Isle Web
- NowChoose the business name and domain, collect your existing content, and prepare the website structure.
- September 21Simon calls to confirm the weather and the first photography visit.
- September 23, morningSimon photographs the first three listings at the two Campbellton Road properties, weather permitting.
- Week of September 28Simon photographs the remaining three PEI listings, weather permitting.
- After the photos arriveI finish the website preview and send it to you for review. The first half of the website payment is due after you approve it.
- OctoberFinish the first site, set up Stripe and prepare for launch.
- NovemberAdd the Deer Island property after its information and photos are ready.
- Over the winterFinish the printed guest guides, Wi-Fi cards and the public availability setup.
Rough dates, we adjust as we go.